Dear All,
Currently we have Windchill Projectlink which is implemented to manage the Project across the Cross Functional teams. I have populated all the activities and RACI has been done and now we have it running in a perfect condition
My concern is:
1. For every document being uploaded and added as deliverables (documents are essentially, word, excel, igs, pdf and ppt and not other data), we have to route it manually for approval or release.
Is there any possible way to get it done automatically for the documents uploaded in Projectlink.
Reason for asking:
Sometimes the users upload the document and set the track work to 100% before getting it to approval stage. Also I would like to ask, if an activity is set as complete, but as an admin I know it is not. Is it possible to revert it back and make users to rework on it.
Thanks in Advance